Thanks, @EliasBrattliSorensen. Regarding the EAP period, the way we understand it, we’ve been in it since March, when we published the first EAP build and the majority of breaking changes you have already seen or experienced. This EAP will be focused on exposing Platform 7 integration, which is the last piece of the puzzle.
If all goes well(the happy path) you can expect
- one more EAP build ~ first half of July - focused on polishing the Platform integration
- RC towards the end of July
Obviously we will be looking into your feedback following the Platform integration EAP and adjust the plan accordingly.
Our goal currently is to have Jira code ready with a given scope so that we can better support you in closing on compatibility.